We are making improvements to the A483 corridor.
Overview
The roads review considered this project
This page reflects our previous road investment programme. A new programme was published in the national transport delivery plan.
We will publish new scheme webpages to reflect the new programme.
Why we are doing it
The A483 junctions 3 to 6 are congested. We want to improve how traffic moves around Wrexham and the areas in this region.
Current progress
We will present the preferred options at a public consultation event to ask stakeholders advice. This information and our evaluation will help us identify the preferred options.
Timetable
Public information events: summer 2020
Identification of a preferred scheme: summer 2020
Public consultation: summer 2020
Public Inquiry (if needed): summer 2021 to autumn 2022
Estimated construction start date (subject to the minister's approval): summer 2023
How we are consulting
We held a 12 week consultation in summer 2020.
Find out more
You can contact us to request further details or provide comments on our proposals at: enquiries@nmwtra.org.uk.